How to calculate concrete slab cost
Start with the dimensions on your plans. For a flat rectangular slab, volume is length × width × thickness, with all measurements in metres. Convert millimetres to metres by dividing by 1,000. Extra concrete is an allowance for your job; the starting 10% is adjustable and does not account for beams or thickened edges.
Enter base preparation, reinforcement and finishing as rates per square metre. Formwork uses the outside perimeter of the rectangle. Enter excavation, delivery and pump hire as whole-job amounts. If the slab has internal edges, steps, multiple levels or irregular shapes, include their additional cost under other costs or obtain a detailed take-off.
Use one GST basis throughout. If your quotes already include GST, leave the inclusive setting selected. If every rate excludes GST, select the exclusive setting and the tool adds 10% after contingency. Contingency is a budgeting reserve, not a supplier charge.
Worked example: a 6 m × 4 m slab
A 24 m² slab at an example thickness of 100 mm contains 2.4 m³. With a 10% allowance, the calculated quantity is 2.64 m³. At the starting example supply rate of $290.90/m³ including GST, that is $767.98 for concrete only.
To show the arithmetic, suppose your own quotes total $2,000 for preparation, reinforcement, formwork and placement, with $121 in delivery fees. The subtotal becomes $2,888.98. A chosen 10% contingency adds $288.90, giving a budget of $3,177.88 including GST, or $132.41/m². The $2,000 is an illustrative input, not a surveyed market price. These figures exclude any unentered pumping, excavation or other charges.
Changing the slab to 150 mm increases its geometric concrete volume by 50%, but does not automatically increase every other cost by 50%. This is why an itemised budget is more useful than multiplying the whole price by thickness. Thickness must follow the design, rather than a budget target. Read the slab thickness requirements guide before using thickness as a quantity input.
Where the starting concrete price comes from
The starting $290.90/m³ is the published GST-inclusive weekday price for the 25/20/80 mix at Cheap Concrete Supplies, checked on 4 November 2026. It is one supplier example, subject to its south-east Queensland delivery area and conditions. It is not an Australian average or a mix specification for your project. Published prices are indicative and can change with the supplier used.
That supplier also lists minimum-load delivery charges, so material volume multiplied by the base rate is not necessarily the invoice total. Replace the starting rate and add delivery fees from your own written quote. The concrete supply prices per m³ guide explains load size, delivery and tax differences.
Holcim publishes separate service fees and surcharges and notes that some are reviewed monthly. Confirm the quote date, unloading allowance, distance charges, minimum cartage and returned-concrete costs before booking. A rate from another city or another month may have a different scope.
What to check before accepting a slab quote
- Design and quantities: thickness, beams, footings, specified mix and reinforcement schedule.
- Groundwork: existing concrete removal, excavation, spoil disposal, base material and compaction.
- Placement: crew, formwork, access, pump minimums, finish and jointing.
- After the pour: curing, protection, cleanup and any sealing included in the price.
- Commercial terms: GST, exclusions, quote validity, variations and delivery charges.
Cement Australia’s small-slab guide illustrates why the job involves formwork, bedding, reinforcement where required, placement and curing. Its small garden slab instructions should not substitute for engineered building slab drawings.
Once quantities are settled, coordinating the crew, pump and delivery matters too. ConConnect is being built for Australian concreters, pump operators and subbies to find work and organise jobs. Join the waitlist if that is the part of the pour you want to make easier.