Free tool · Australian dollars

Concrete Slab Cost Calculator Australia

Work out your slab volume, then build an itemised budget using your own material and labour quotes. See how thickness, preparation, pumping and GST change the cost per m².

Do not have quoted rates yet? Use the quick installed-cost estimator for an initial area-and-finish budget, then return here to itemise your quotes.

1. Slab dimensions
m
m
mm
%

100 mm is an example input, not a design recommendation. Enter the thickness on your plans. Beams and thickened edges need a separate take-off.

2. Enter your quoted rates

The starting concrete rate is one published supplier example, checked 4 November 2026. Every other cost starts at $0: add your quotes for a fuller budget. Leave an item at zero only if it is excluded or already covered elsewhere.

$/m³
$/m²
$/m²
$/m²
$/m
$
$
$
$
%
3. GST treatment

Concrete supply only · AUD

$767.98

$32.00 per m² · 24.00 m² · includes GST

This is not a full slab installation budget. Preparation, reinforcement, labour, formwork and delivery currently have no allowance.

Slab volume

2.400 m³

With allowance

2.640 m³
Concrete supply
$767.98
Base preparation
$0.00No allowance
Reinforcement and supports
$0.00No allowance
Placement and finishing
$0.00No allowance
Formwork
$0.00No allowance
Excavation and spoil removal
$0.00No allowance
Pump hire
$0.00No allowance
Delivery and supplier fees
$0.00No allowance
Other costs
$0.00No allowance
Contingency
$0.00No allowance
GST added
$0.00

This is the sum of the costs entered, not an installed-price quote. Zero allowances are not free work. Confirm minimum order quantities and truck increments with your supplier before ordering.

How to calculate concrete slab cost

Start with the dimensions on your plans. For a flat rectangular slab, volume is length × width × thickness, with all measurements in metres. Convert millimetres to metres by dividing by 1,000. Extra concrete is an allowance for your job; the starting 10% is adjustable and does not account for beams or thickened edges.

Slab budget = concrete supply + preparation + reinforcement + formwork + placement + fixed charges + contingency + any GST to add.

Enter base preparation, reinforcement and finishing as rates per square metre. Formwork uses the outside perimeter of the rectangle. Enter excavation, delivery and pump hire as whole-job amounts. If the slab has internal edges, steps, multiple levels or irregular shapes, include their additional cost under other costs or obtain a detailed take-off.

Use one GST basis throughout. If your quotes already include GST, leave the inclusive setting selected. If every rate excludes GST, select the exclusive setting and the tool adds 10% after contingency. Contingency is a budgeting reserve, not a supplier charge.

Worked example: a 6 m × 4 m slab

A 24 m² slab at an example thickness of 100 mm contains 2.4 m³. With a 10% allowance, the calculated quantity is 2.64 m³. At the starting example supply rate of $290.90/m³ including GST, that is $767.98 for concrete only.

To show the arithmetic, suppose your own quotes total $2,000 for preparation, reinforcement, formwork and placement, with $121 in delivery fees. The subtotal becomes $2,888.98. A chosen 10% contingency adds $288.90, giving a budget of $3,177.88 including GST, or $132.41/m². The $2,000 is an illustrative input, not a surveyed market price. These figures exclude any unentered pumping, excavation or other charges.

Changing the slab to 150 mm increases its geometric concrete volume by 50%, but does not automatically increase every other cost by 50%. This is why an itemised budget is more useful than multiplying the whole price by thickness. Thickness must follow the design, rather than a budget target. Read the slab thickness requirements guide before using thickness as a quantity input.

Where the starting concrete price comes from

The starting $290.90/m³ is the published GST-inclusive weekday price for the 25/20/80 mix at Cheap Concrete Supplies, checked on 4 November 2026. It is one supplier example, subject to its south-east Queensland delivery area and conditions. It is not an Australian average or a mix specification for your project. Published prices are indicative and can change with the supplier used.

That supplier also lists minimum-load delivery charges, so material volume multiplied by the base rate is not necessarily the invoice total. Replace the starting rate and add delivery fees from your own written quote. The concrete supply prices per m³ guide explains load size, delivery and tax differences.

Holcim publishes separate service fees and surcharges and notes that some are reviewed monthly. Confirm the quote date, unloading allowance, distance charges, minimum cartage and returned-concrete costs before booking. A rate from another city or another month may have a different scope.

What to check before accepting a slab quote

  • Design and quantities: thickness, beams, footings, specified mix and reinforcement schedule.
  • Groundwork: existing concrete removal, excavation, spoil disposal, base material and compaction.
  • Placement: crew, formwork, access, pump minimums, finish and jointing.
  • After the pour: curing, protection, cleanup and any sealing included in the price.
  • Commercial terms: GST, exclusions, quote validity, variations and delivery charges.

Cement Australia’s small-slab guide illustrates why the job involves formwork, bedding, reinforcement where required, placement and curing. Its small garden slab instructions should not substitute for engineered building slab drawings.

Once quantities are settled, coordinating the crew, pump and delivery matters too. ConConnect is being built for Australian concreters, pump operators and subbies to find work and organise jobs. Join the waitlist if that is the part of the pour you want to make easier.

FAQs

How do I calculate the cost of a concrete slab?

Calculate the slab volume in cubic metres, add your agreed extra-volume allowance and multiply by your supplier's rate. Then add base preparation, reinforcement, formwork, placement, excavation, delivery and any pump hire. Keep every input on the same GST basis. This calculator itemises those amounts instead of assuming one installed rate fits every job.

How much concrete is needed for a 6 m × 4 m slab?

At an example thickness of 100 mm, a flat 6 m × 4 m slab contains 2.4 m³. A 10% extra-volume allowance makes 2.64 m³. Beams, thickened edges and footings are additional, and your supplier may use minimum quantities or ordering increments. Use the thickness specified for your project.

Does the calculator include labour, steel and site preparation?

Only when you enter those rates. They start at zero to avoid presenting invented national prices. A zero amount means no allowance has been added. If a contractor gives you an inclusive installed rate, do not add the same materials and labour a second time.

Can I use this for a shed or house slab?

You can use it to budget the flat portion of a slab. It does not take off engineered beams, ribs, footings or reinforcement schedules. For a house slab or an engineered shed slab, have quantities checked against the drawings and include those additional costs separately.

Why does a small concrete slab cost more per square metre?

Some costs do not shrink with the slab area: mobilisation, pump minimums, delivery minimums, formwork setup and crew time still apply. Dividing those costs across fewer square metres increases the effective rate.

Plan the pour as well as the price

ConConnect is being built to help Australian concreters, pump operators and subbies find work and organise jobs. Join the waitlist for launch updates.