Concrete pump hire cost

By the ConConnect team · Updated September 2026 · Published rate examples checked 12 September 2026

Pump hire is usually a fee stack rather than one hourly number. Published examples accessed for this guide list line-pump rates of $170/hour in Sydney and $200/hour in Geelong, both with four-hour minimums and both ex-GST. Your invoice can also include travel, volume, setup, washout and labour. Enter your quote below to see the complete total.

Pump quote breakdown calculator

Enter the figures from a pump quote. Blank optional charges count as zero.

Time and volume
$/hr
hrs
hrs
$/m³
Other quoted charges
$
$
$
$
$

The Sydney example uses CJR Concrete Pumping's published line pump schedule accessed 12 September 2026. Replace every field with your provider's quote before relying on the result.

Estimated invoice total

$0.00

Billed time (0.00 hrs)
$0.00
Volume charge
$0.00
Other charges
$0.00
Subtotal$0.00
GST$0.00

Estimate only. This adds the values you enter; it does not choose a pump, confirm availability or replace the provider's final quote and site assessment.

Published concrete pump hire rates

These are dated observations from three operators, not a national average. Equipment, crew, location, site conditions and booking time all affect a firm quote. Each linked source should be checked again before booking because providers can change their rates.

CJR Concrete Pumping

Sydney, NSW

Line-pump observation
$170/hr
Minimum
4 hours
Other published charges
$170 travel, $7/m³, $12 setup

Page modified 29 Jan 2025; accessed 12 Sep 2026

Jagcor Concrete Pumping

Geelong, VIC

Line-pump observation
$200/hr
Minimum
4 hours
Other published charges
$7/m³; local travel charged at half the pump rate

Publication date not shown; accessed 12 Sep 2026

Hunter Concrete Pumps

Newcastle and Hunter, NSW

Line-pump observation
$180–$220/hr starting guide
Minimum
Varies by quote
Other published charges
Small-pour flat rate from $800; travel varies

Published 1 Jul 2026; accessed 12 Sep 2026

Rates shown in the sources are ex-GST. Hunter's figures are a local planning guide; CJR and Jagcor publish rate schedules.

Worked example: CJR Sydney line-pump schedule

Four billed hours at $170 = $680, plus $170 travel, 6 m³ at $7 = $42, and $12 setup. That is $904.00 ex-GST, $90.40 GST and $994.40 total. Use “Load Sydney example” in the calculator to reproduce it, then replace each field with your own quote.

How the total is calculated

The calculator first bills the greater of expected onsite time and minimum hire. It then adds volume and the other quoted fees. GST is added only when the switch is on.

total = hourly rate × billed hours + volume charge + other fees + GST

Billed onsite time

The hourly rate is multiplied by the greater of expected onsite time and the supplier's minimum hire.

Travel or mobilisation

This may be a fixed amount, billed time, a per-kilometre charge or a location-based quote.

Concrete pumped

Some schedules add a charge for each cubic metre. Enter zero in the calculator when your quote does not.

Setup, slurry and washout

Check whether these are included and whether a suitable washout area changes the fee.

Labour, spotters and timing

Extra crew, after-hours work and weekend bookings can have separate rates or minimums.

GST

The published examples below are ex-GST. Confirm the treatment on every quote before comparing totals.

Line pump or boom pump?

Safe Work Australia distinguishes line pumps by their flexible delivery hoses and mobile placing booms by their boom-supported pipework. Use the questions below to prepare the job details, then let the pump provider confirm the equipment and safe setup for the site.

How concrete reaches the pour

Line pump
Flexible delivery hoses run from a trailer- or truck-mounted pump.
Mobile boom pump
Pipework is supported by a multi-stage boom mounted on the truck.

Useful site question

Line pump
Can a safe hose route reach the forms, including bends and changes in level?
Mobile boom pump
What horizontal and vertical reach is required over obstacles or structures?

Setup question

Line pump
Where can the pump and delivery truck stand, and who will manage the hose?
Mobile boom pump
Is there suitable space and ground for the truck, outriggers and boom movement?

Quote detail to confirm

Line pump
Included hose length, long-line charges, crew and compatible concrete mix.
Mobile boom pump
Required boom size, reach, setup conditions, crew and any spotter or traffic needs.

Source: Safe Work Australia's concrete pumping overview. Site-specific legal and safety requirements depend on the jurisdiction and work; follow the applicable regulator and provider.

What to send for an itemised quote

WorkSafe Queensland says planning should begin early and involve the people responsible for the site and pumping work. A clear brief helps the provider assess access, placement and the fee structure before the booking.

Read the regulator's planning and site-preparation guidance, and use the guidance for your state or territory.

  • Measured concrete volume, plus the order quantity agreed with the concreter or supplier
  • Pour address, date, start time and expected onsite duration
  • Photos or a plan showing truck access, pump position and the route to the forms
  • Horizontal distance, changes in level and any buildings, fences or other obstacles
  • Nearby powerlines, roads, footpaths or public areas that the provider must assess
  • Available washout area, water and site facilities
  • Who supplies hose hands, spotters, traffic control or other labour
  • Whether hourly minimums, travel, volume, setup, washout, cancellation and GST are included

Still measuring the pour? Calculate the concrete volume first. For the wider installed-job budget, use the concrete cost calculator.

Concrete pump hire FAQs

How much does concrete pump hire cost?

There is no single Australia-wide rate. Published examples accessed in September 2026 include a Sydney line-pump schedule at $170 per hour with a four-hour minimum and a Geelong schedule at $200 per hour with a four-hour minimum, both ex-GST. Travel, volume, setup, washout, labour and timing can change the final invoice, so compare the complete fee stack.

What is the minimum hire for a concrete pump?

Both the CJR Sydney and Jagcor Geelong rate pages accessed for this guide publish a four-hour onsite minimum for their standard line-pump pricing. Minimums are supplier- and booking-specific, so enter the minimum shown on your own quote in the calculator.

Are concrete pump hire rates quoted with GST?

The three published examples used in this guide present their displayed rates or guide table as ex-GST. Check your provider's wording: if the quote is ex-GST, leave the calculator's Add 10% GST switch on; if the total already includes GST, switch it off.

What is the difference between a line pump and a boom pump?

Safe Work Australia describes line pumps as trailer- or truck-mounted pumps using flexible hoses. Mobile concrete placing booms use truck-mounted pumps with pipework supported by a multi-stage boom. The provider should confirm which setup suits the route, reach, volume and site conditions.

What information should I send for a pump quote?

Send the pour address and timing, concrete volume, photos or plans of access, the route and distance to the forms, changes in level, obstacles, nearby powerlines or public areas, washout availability and the labour you can supply. Ask for every minimum, travel, volume, setup, washout, timing and GST charge to be itemised.

Book pumps without the phone chase.

ConConnect is being built for concreters and pump operators to find each other, organise jobs and keep work moving. Join the waitlist for launch access and three months of Plus free.