The specified mix
Ask for the same strength, aggregate size, slump and any specified additives on every quote. Pump mixes, colour, fibres and special performance requirements can change the price. Our fibre types and uses guide distinguishes the reinforcement roles to discuss with the supplier. Keep the project specification: a cheaper strength is not a substitute for the mix required by the plans.
Minimum loads, distance and waiting time
Boral's NSW Metro schedule, effective 14 October 2026, lists these fees excluding GST:
- Loads below 3 m³: $98.40 per missing m³ up to 3 m³, rather than buying extra concrete at the material rate.
- Extra cartage beyond 15 km from the nearest plant: $3.30 per m³ per kilometre.
- Unloading beyond 30 minutes from arrival: $3.90/minute in normal hours, or $7.70/minute outside them.
- Saturday afternoon cartage: $70/m³; Sunday/public holiday cartage: $110/m³. Plant opening can be another fee.
These conditions belong to that region and schedule. They do not apply automatically to another supplier or to every Boral location. Confirm load-by-load charging and normal hours.
Separate surcharges and inconsistent inclusions
Holcim's 20 March 2026 notice introduced an $8.67/m³ production and transport surcharge excluding GST from 1 April, with monthly review. That is a dated illustration of a separate fee, not a claim that April's amount still applies in November. Ask which surcharges are already included in your quote.
Eureka's April 2026 surcharge page lists normal-hours excess discharge after 45 minutes at $3.30/minute including GST, plus minimum-load and weekend conditions. Its mini-distance figure differs from its pricing page. Ask the supplier to reconcile the schedules and confirm whether a mini-mix quantity price includes minimum-load charges before adding anything.